MOUNT SINAI CT ROOM RENOVATION
Construction Management
Renovation of an existing CT Main Room, Control Room and Equipment Room to accommodate the replacement and installation of a new Siemens Somatom 64 Slice CT. The scope includes new Siemens CT and corresponding equipment, electrical feeders’ reconfiguration, electrical panels, HVAC equipment, new interior finishes, solid surface and millwork. ICRA: Type D, Highest Risk
KEY FACTS
Cost: $65 K
Completion: 06/2017
Owner: Mount Sinail Medical Center